Free tools · Document search
Search the Gazettes and decisions
The full text of every Government Gazette and NERSA decision our figures come from, page by page. Type a phrase and go straight to the page that prints it, in our stored copy or at the source.
387 pages with all the words free basic electricity.
-
Decision and Reasons for Decision, Dipaleseng, FY2026/27
NERSA file 9422
… The licensee provides 50 kWh free basic electricity (FBE) to 851 indigent customers. Table 1: Customer base 2024-25 Customer Customer categories MWh % MWh …
Page 7 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Knysna, FY2026/27
NERSA file 9220
… KLM provides qualifying indigent customers with 50 kWh of Free Basic Electricity (FBE) per month and maintains an indigent register. Details of the municipality …
Page 7 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Langeberg, FY2026/27
NERSA file 9222
… LM provides qualifying indigent customers with 50 kWh of Free Basic Electricity (FBE) per month and maintains an indigent register. Details of the municipality …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Blouberg, FY2026/27
NERSA file 9261
… The municipality provides its indigent customers with 50kWh of Free Basic Electricity (FBE) per month. The municipality further reports that it maintains an indigent …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Kannaland, FY2026/27
NERSA file 9219
… KLM provides qualifying indigent customers with 50 kWh of free basic electricity (FBE) per month and maintains an indigent register. Details of the municipality …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Nkomazi, FY2026/27
NERSA file 9409
… Eskom supplies 50kWh of free basic electricity per month to all registered indigent customers. Details regarding customer statistics are highlighted in Table 1 below …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Laingsburg, FY2026/27
NERSA file 9221
… LM provides qualifying indigent customers with 50 kWh of Free Basic Electricity (FBE) per month and maintains an indigent register. Details of the municipality …
Page 5 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Magareng, FY2026/27
NERSA file 9287
… The Municipality provides its indigent customers with a minimum of 50kWh of Free Basic Electricity (FBE) per month. The details regarding customer statistics are …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Msukaligwa, FY2026/27
NERSA file 9199
… The Municipality provides 50 kWh of free basic electricity per month to its 3 370 registered indigent customers. 1.3. Table 1 below highlights …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
-
Decision and Reasons for Decision, Greater Tzaneen, FY2026/27
NERSA file 9202
… The municipality has confirmed that it does have an indigent register and 23 indigent customers and provides 50kWh free basic electricity per month to …
Page 6 in our copyOfficial source
National Energy Regulator of South Africa, its decision as published on nersa.org.za
Only official texts are here: Government Gazettes from the Government Printing Works and decisions of the National Energy Regulator (NERSA), which the Copyright Act (s12(8)(a)) leaves free of copyright. Each result names its publisher and links to the official copy. Our copy is the file we read the figures from, fingerprinted (sha256). Reports from the Department of Water and Sanitation aren’t here, as their terms don’t say they may be republished. The pages of NERSA decisions that list objectors and comments (455 pages) are left out, as they name people; in our copies of those decisions each such page is replaced by a page saying it is withheld, and the whole decision is on NERSA’s site. Pages printed as pictures are found only where we read them for a dataset. As data: /api/search/documents?q=.