Notices·Regulator’s decision·30 April 2026

Decision and Reasons for Decision, Cape Agulhas, FY2026/27

Issued by the National Energy Regulator of South Africa, dated 30 April 2026.

01

What it is

Kind

Regulator’s decision

NERSA file 9204.

Issued by

National Energy Regulator of South Africa

Used for

Electricity tariffs

31 records in our data are built from it.

02

Every figure it set

145 figures, each as the document prints it, with the page it is on where the document has pages. Grouped by the record built from it.

Cape Agulhas: Domestic high, single phase (conventional or prepaid, above 30 A)financial year 2026/27

Record za-wc033-domestic-high-single-phase-conventional-or-prepaid-above-30-a-2026-27 · Cape Agulhas

Cape Agulhas: Domestic high, three phase (conventional or prepaid, above 30 A)financial year 2026/27

Record za-wc033-domestic-high-three-phase-conventional-or-prepaid-above-30-a-2026-27 · Cape Agulhas

Cape Agulhas: Domestic indigent (prepaid and conventional, up to 20 A)financial year 2026/27

Record za-wc033-domestic-indigent-prepaid-and-conventional-up-to-20-a-2026-27 · Cape Agulhas

Cape Agulhas: Domestic prepaid (30 A)financial year 2026/27

Record za-wc033-domestic-prepaid-30-a-2026-27 · Cape Agulhas

Cape Agulhas: Commercial small consumer, prepaid (up to 20 A, single phase)financial year 2026/27

Record za-wc033-commercial-small-consumer-prepaid-up-to-20-a-single-phase-2026-27 · Cape Agulhas

Cape Agulhas: Industrial, time of use (11 000 V)financial year 2026/27

Record za-wc033-industrial-time-of-use-11-000-v-2026-27 · Cape Agulhas

Cape Agulhas: Industrial, time of use (380/220 V)financial year 2026/27

Record za-wc033-industrial-time-of-use-380-220-v-2026-27 · Cape Agulhas

Cape Agulhas: Agricultural small holdings: Prepaid (up to 20 A, single phase)financial year 2026/27

Record za-wc033-agricultural-small-holdings-prepaid-up-to-20-a-single-phase-2026-27 · Cape Agulhas

Cape Agulhas: SSEG fixed network charge: 0 kW to 6.8 kW (30 A)financial year 2026/27

Record za-wc033-sseg-fixed-network-charge-0-kw-to-6-8-kw-30-a-2026-27 · Cape Agulhas

Cape Agulhas: SSEG fixed network charge: 11.5 kW and above (60 A)financial year 2026/27

Record za-wc033-sseg-fixed-network-charge-11-5-kw-and-above-60-a-2026-27 · Cape Agulhas

Cape Agulhas: SSEG fixed network charge: 6.9 kW to 9.1 kW (40 A)financial year 2026/27

Record za-wc033-sseg-fixed-network-charge-6-9-kw-to-9-1-kw-40-a-2026-27 · Cape Agulhas

Cape Agulhas: SSEG fixed network charge: 9.2 kW to 11.4 kW (50 A)financial year 2026/27

Record za-wc033-sseg-fixed-network-charge-9-2-kw-to-11-4-kw-50-a-2026-27 · Cape Agulhas

Cape Agulhas: SSEG import energy chargefinancial year 2026/27

Record za-wc033-sseg-import-energy-charge-2026-27 · Cape Agulhas

Cape Agulhas: Public schools and hostels: Prepaid (up to 20 A, single phase)financial year 2026/27

Record za-wc033-public-schools-and-hostels-prepaid-up-to-20-a-single-phase-2026-27 · Cape Agulhas

Cape Agulhas: Public schools, hostels, charity and welfare organisations: Single phase, prepaid or over 20 Afinancial year 2026/27

Record za-wc033-public-schools-hostels-charity-and-welfare-organisations-single-phase-prepaid-or-over-20-a-2026-27 · Cape Agulhas

03

The document

The file our figures were read from. The copy shown here has some pages withheld, so there are two fingerprints below: the copy’s and the original’s.

Check it yourself

SHA-256 of the copy we showb3d114eac2733ca83eb5368ab6bc6e1b8b8df3db2a25023c24b97cf251bbefa9

SHA-256 of the original, kept and not shownad3d4861ba739dc3d8133f3fcb434911d6be909449ffe91b3eef6cd993fe51b0

  1. Download our copy with the link above. 2 pages of it are replaced by a note, because the original’s name members of the public.
  2. Work out the file’s fingerprint. Mac or Linux: shasum -a 256 the-file.pdf. Windows: certutil -hashfile the-file.pdf SHA256.
  3. It should give the first fingerprint above: the copy’s own.
  4. The second is the file as we fetched it from the publisher. A copy from the publisher’s own site gives it only if they have not changed their file since.

A fingerprint shows a file has not changed. It is not encryption. How this works

04

Where its figures are used

Electricity tariffsEvery releaseEvery notice

How to read this page

  1. Every figure is as the document prints it, with the page it is on where the document has pages.
  2. A date links to its own page, with everything else that changed that day.
  3. Old figures are kept, never overwritten. A notice page lists what the notice set, even after a later one replaced it.
  4. Hatching means we hold no copy. Such a source is cited only, and its page says so.