Decision and Reasons for Decision, Langeberg, FY2026/27

Issued by the National Energy Regulator of South Africa, dated 6 May 2026.

01

What it is

Kind

Regulator’s decision

NERSA file 9222.

Issued by

National Energy Regulator of South Africa

Used for

Electricity tariffs

30 records in our data are built from it.

02

Every figure it set

174 figures, each as the document prints it, with the page it is on where the document has pages. Grouped by the record built from it.

Langeberg: 1. Domestic indigent, single phase, up to 60 Afinancial year 2026/27

Record za-wc026-1-domestic-indigent-single-phase-up-to-60-a-2026-27 · Langeberg

Langeberg: 2. Domestic, single phase, up to 60 Afinancial year 2026/27

Record za-wc026-2-domestic-single-phase-up-to-60-a-2026-27 · Langeberg

Langeberg: 3. Domestic, three phase, up to 80 Afinancial year 2026/27

Record za-wc026-3-domestic-three-phase-up-to-80-a-2026-27 · Langeberg

Langeberg: 4. Domestic indigent, conventional, single phase, up to 60 Afinancial year 2026/27

Record za-wc026-4-domestic-indigent-conventional-single-phase-up-to-60-a-2026-27 · Langeberg

Langeberg: 5. Domestic, conventional, single phase, up to 60 Afinancial year 2026/27

Record za-wc026-5-domestic-conventional-single-phase-up-to-60-a-2026-27 · Langeberg

Langeberg: 6. Domestic, conventional, three phase, up to 80 Afinancial year 2026/27

Record za-wc026-6-domestic-conventional-three-phase-up-to-80-a-2026-27 · Langeberg

Langeberg: 7. Commercial: Prepaid business, single phase, up to 60 Afinancial year 2026/27

Record za-wc026-7-commercial-prepaid-business-single-phase-up-to-60-a-2026-27 · Langeberg

Langeberg: 8. Commercial: Prepaid business, three phase, up to 80 Afinancial year 2026/27

Record za-wc026-8-commercial-prepaid-business-three-phase-up-to-80-a-2026-27 · Langeberg

Langeberg: 13. Industrial and bulk: Normal bulk, large power user, below 11 kVfinancial year 2026/27

Record za-wc026-13-industrial-and-bulk-normal-bulk-large-power-user-below-11-kv-2026-27 · Langeberg

Langeberg: 14. Industrial and bulk: Normal bulk, large power user, 11 kVfinancial year 2026/27

Record za-wc026-14-industrial-and-bulk-normal-bulk-large-power-user-11-kv-2026-27 · Langeberg

Langeberg: 15. Industrial and bulk: Normal bulk, large power user, below 11 kV, time of usefinancial year 2026/27

Record za-wc026-15-industrial-and-bulk-normal-bulk-large-power-user-below-11-kv-time-of-use-2026-27 · Langeberg

Langeberg: 16. Industrial and bulk: Normal bulk, large power user, 11 kV, time of usefinancial year 2026/27

Record za-wc026-16-industrial-and-bulk-normal-bulk-large-power-user-11-kv-time-of-use-2026-27 · Langeberg

Langeberg: 21. Bulk consumers permanently exceeding their notified maximum demandfinancial year 2026/27

Record za-wc026-21-bulk-consumers-permanently-exceeding-their-notified-maximum-demand-2026-27 · Langeberg

Langeberg: 17. Street lighting: Departmentalfinancial year 2026/27

Record za-wc026-17-street-lighting-departmental-2026-27 · Langeberg

Langeberg: Street lighting: Non-departmental consumptionfinancial year 2026/27

Record za-wc026-street-lighting-non-departmental-consumption-2026-27 · Langeberg

Langeberg: 18. Sportsgrounds: Prepaid, single phase up to 60 A and three phase up to 80 Afinancial year 2026/27

Record za-wc026-18-sportsgrounds-prepaid-single-phase-up-to-60-a-and-three-phase-up-to-80-a-2026-27 · Langeberg

Langeberg: 19. Unmetered points: Telkom, below 10 Afinancial year 2026/27

Record za-wc026-19-unmetered-points-telkom-below-10-a-2026-27 · Langeberg

Langeberg: 20. Availability fee: Erven of 200 m2 and largerfinancial year 2026/27

Record za-wc026-20-availability-fee-erven-of-200-m2-and-larger-2026-27 · Langeberg

Langeberg: 20. Prepaid electricity coupon feefinancial year 2026/27

Record za-wc026-20-prepaid-electricity-coupon-fee-2026-27 · Langeberg

03

The document

The file our figures were read from. The copy shown here has some pages withheld, so there are two fingerprints below: the copy’s and the original’s.

Check it yourself

SHA-256 of the copy we show087c651c26f81e057649a9073776b48731d5929105361adb016fb182e9b7fc36

SHA-256 of the original, kept and not shown577c81f1976eb17d87057adf697f8875be222940caf08ba8521b24e2cf17116c

  1. Download our copy with the link above. 3 pages of it are replaced by a note, because the original’s name members of the public.
  2. Work out the file’s fingerprint. Mac or Linux: shasum -a 256 the-file.pdf. Windows: certutil -hashfile the-file.pdf SHA256.
  3. It should give the first fingerprint above: the copy’s own.
  4. The second is the file as we fetched it from the publisher. A copy from the publisher’s own site gives it only if they have not changed their file since.

A fingerprint shows a file has not changed. It is not encryption. How this works

04

Where its figures are used

Electricity tariffsEvery releaseEvery notice

How to read this page

  1. Every figure is as the document prints it, with the page it is on where the document has pages.
  2. A date links to its own page, with everything else that changed that day.
  3. Old figures are kept, never overwritten. A notice page lists what the notice set, even after a later one replaced it.
  4. Hatching means we hold no copy. Such a source is cited only, and its page says so.

Every notice and decision

Unmapped Dataworks